By Tony Davis, owner, Davis Construction & Home Improvement (MHIC #118450)
After the permit comes through and the material is delivered, a 12×12 deck takes us two to three days, a 12×25 takes three to five, and a big 16×40 takes six to eight. Multi-level decks, covered decks and screened porches run one to two weeks. The county permit review comes before that. St. Mary’s County’s deck guide gives no fixed review time, and Calvert County says its timeline varies by project complexity, so this post covers both.
On This Page
ToggleBuild times on site
| Project | Build time |
|---|---|
| 12×12 deck | 2–3 days |
| 12×25 deck | 3–5 days |
| 16×40 deck | 6–8 days |
| Multi-level deck | 1–2 weeks |
| Re-deck (resurfacing) | Same as a new deck of that size |
| Covered deck (12×16 with lean-to roof) | 1–2 weeks |
| Screened porch (12×16) | 1–2 weeks |
| Pergola (12×12) on its own | 3–5 days |
| Pergola built with a deck | 1–2 weeks |
| Three-season room (16×20) | 1–2 weeks |
| Four-season room (16×20) | 1½–2 weeks |
These times count from the day construction starts on your property.
What happens before the first post goes in
1. Free estimate and design
Tony visits and brings product samples. Every quote comes with a free 3D drawing, so you see the deck before signing. You can book through our online calendar.
2. Signing
When the design and price are right, you sign and pay 30%.
3. The permit
We pull a permit on every deck we build. How the review goes depends on your county.
St. Mary’s County. According to the county’s deck guide, every deck needs a building permit, and the guide says to use the county’s “On Demand” process to get it. The application needs a plot plan drawn to scale showing the house, the deck and its dimensions, and its position relative to property lines. If the home is on a private well or septic system, the Health Department reviews it too, and the guide notes that review isn’t guaranteed to be on-demand. The guide doesn’t publish a standard review time.
Calvert County. Residential decks require a building permit, as do repairs or changes to a deck’s structure, stairs or railing. Decks within the Critical Area (land within 1,000 feet of the mean high water line of tidal waters or the landward edge of tidal wetlands) also need a Critical Area Worksheet, and homes on well or septic get an Environmental Health review. The county’s residential permitting process runs from application and intake through agency review, any revisions, and issuance, and the county says the timeline varies by project complexity.
We pull the permit for you.
4. Material delivery
Construction starts once the permit is issued and the material is on site. The 60% payment comes due the day work begins.
On-site sequence
- Tear-out. If there’s an old deck, we remove it, haul it away and pay the dump fees. That’s part of the price.
- Footings. Holes go 24 to 30 inches into the ground at 18 inches wide, and the inspector looks at them. St. Mary’s County’s guide says the inspection fee and completed inspection form must be on file 24 hours before the footing inspection is requested.
- Framing. Built from No. 1 grade ground-contact lumber; the framing inspection comes next.
- Decking, railing and steps. Composite goes down with hidden fasteners, Fiberon with EDGE or EDGEX clips. Railings and stairs follow.
- Final inspection. We handle the inspection and try to be on site when the inspector comes. After it passes, the last 10% is due.
Our process page goes through each stage in more detail.
Things that can add time
- Rot found on a re-deck. The cost of up to two bad 12-foot joists is already built in. Find more than that, and we pause, show you, and get a signed amendment before the crew continues.
- Roofs and walls. A covered deck, screened porch or three-season room runs one to two weeks on our schedule.
- Extra levels. A multi-level deck is one to two weeks.
- County review. Extra reviews, such as Critical Area or Health Department, can add steps before a permit is issued.
Timeline questions
Is a re-deck faster than a brand-new deck?
No. Resurfacing carries the same build time as a new deck of that size. It still gets new decking, railings, fascia and rebuilt steps.
Can I get my deck before a party?
Tell us the date at the estimate. Our build times are listed above; the permit review timeline is set by the county, so earlier is better.
Does a pergola slow down a deck build?
A 12×12 pergola alone takes three to five days. Built together with a deck, the combined project runs one to two weeks. See pergolas.
The clock starts at the free estimate visit, and payments line up with the build as shown in our 30/60/10 payment guide.
Start the clock
The sooner the estimate happens, the sooner the permit goes in. Choose a free estimate time or call Tony directly at 240-794-2274.
Sources: St. Mary’s County, Building Permits for Decks (CAG-4); Calvert County, Deck – Residential; Calvert County, Residential Permitting Process. Build times and process come from Davis Construction’s own price list.


