  • Deck Permits in Charles County: Inspections, Footings and the 2021 Code

Charles County’s building code adds its own deck inspections on top of the model code. It requires a footing inspection on every deck application, a separate framing inspection on decks built close to the ground, and a preliminary look at the house wall before a ledger goes on. This post walks through those rules as the county wrote them, and how we plan a Charles County job around them.

The code Charles County uses today

Charles County adopted the 2021 International Residential Code under Bill 2024-10. The county’s Planning and Growth Management notice (#24-01) says the update applies to all building and trade permit applications received on or after June 28, 2024. The local changes live in Chapter 224 of the County Code, “Building Construction.”

If you see a deck article quoting older Charles County rules, check the date. Anything written before mid-2024 may be citing the previous code.

Four inspection points

Chapter 224 adds deck-specific inspections to the IRC’s list of other inspections. The fourth one, the final, is the last step on every job we build.

1. Preliminary inspection (ledger decks)

Section R109.1.5.4 says, “A preliminary inspection shall be required for all ledger supported decks.” The framing of the house where the ledger will attach has to be exposed and inspected before the ledger goes on. In plain terms, the inspector sees what the ledger will be fastened to before it’s covered up.

2. Footing inspection (every deck)

Section R109.1.5.2 reads, “A footing inspection shall be required for all deck applications.” It must be approved before concrete is placed, and before any framing goes in that would block access to the footing holes.

3. Framing inspection (low decks)

Section R109.1.5.3 requires “a separate deck framing inspection” before any surface decking is installed, wherever any part of the beams or joists (landings and stairways excluded) has less than 4 feet of clearance above grade. Trim boards and lattice that could hide framing fasteners and connections can’t go on until the framing is approved.

4. Final inspection

We handle the final inspection when the deck is finished, just as we handle the footing and framing inspections, and we try to be on site whenever the inspector comes. Our last 10% payment isn’t due until the final passes.

Because of that framing rule, skirting on a low deck here can’t go on until the framing inspection is approved. Our deck framing page covers what goes under the decks we build.

Footing rules written into the county code

Charles County’s amendment to IRC Section R403.1.4 sets three requirements:

  • Exterior footings “shall not be placed less than 24″ below the undisturbed ground surface,” except in the county’s area of geotechnical concern, which has its own rules.
  • “All deck and stair support posts shall bear on a minimum 16″ x 16″ x 8″, or 18″ round concrete footings.”
  • Footings within five feet of an existing foundation must go as deep as that foundation’s footings, unless a Maryland-licensed professional provides an engineered report showing code compliance.

The county’s climatic design table also lists the frost line depth at 24 inches.

Our standard footing goes down 24–30 inches with an 18-inch width. That meets the county’s 24-inch minimum depth, and where a footing lands within five feet of your house foundation, the county’s match-the-foundation rule controls how deep it goes.

Is any deck exempt?

Charles County also rewrote item 10 under “Building” in the IRC’s list of work exempt from permit (Section R105.2): the wording “are not attached to a dwelling” was replaced with “not supported by attachment to a dwelling, or adjacent structure.” We don’t rely on the exemption at all. Every deck we build gets a permit, and Davis Construction pulls it.

Stair numbers are different here

Charles County also amended the stair dimensions. The county’s text replaces the model code’s 7¾-inch maximum riser with 8¼ inches, and the 10-inch minimum tread with 9 inches. Winder treads get the same 10-to-9 change.

What the inspections mean for your schedule and price

Inspections add waiting points between steps, but they don’t add a line to our price. The permit sits inside every total we quote, right next to footings, railings, labor, materials, hardware, tear-out of any existing deck, and hauling and disposal. For example, a 12×12 pressure-treated deck is $10,080 and a 12×12 deck in Trex Select or TimberTech Terrain is $13,680, with the permit already in those numbers. Every size and material is listed in our Southern Maryland deck prices.

Our build times are 2–3 days for a 12×12, 3–5 for a 12×25 and 6–8 for a 16×40, and the county’s footing inspection has to be approved before any concrete is placed.

Charles County deck permit questions

Why does the inspector need to see my house framing?

Because the county code requires a preliminary inspection on every ledger-supported deck, with the framing at the ledger exposed. It lets the inspector confirm what the ledger is being fastened to before it’s covered.

My deck is 6 feet off the ground. Is there still a framing inspection?

The separate framing inspection in R109.1.5.3 is triggered where beams or joists have under 4 feet of clearance.

Can I replace a deck that’s near my foundation with shallower footings?

Not within five feet of the foundation unless an engineered report from a Maryland-licensed professional supports it. The county requires those footings to match the depth of the existing foundation footings.

Talk to us about your Charles County deck

Pick a free estimate time here or dial 240-794-2274 to reach Tony. Expect product samples on the visit and a 3D design of your deck with the quote at no charge. Military veterans and active-duty members: 10% comes off, to a $1,000 maximum. See our Charles County deck builder page for more.

Sources: Charles County Bill 2024-10, Charles County Building Code (amending Chapter 224, Building Construction); Charles County Planning & Growth Management Notice #24-01, 2021 Building Code Update. Prices and process come from Davis Construction’s own price list.

Share this post

Subscribe to our newsletter

Keep up with the latest blog posts by staying updated. No spamming: we promise.
By clicking Sign Up you’re confirming that you agree with our Terms and Conditions.

Related posts

Maryland Home Improvement Commission (MHIC) License #118450 · Licensed & Insured