By Tony Davis, owner, Davis Construction & Home Improvement (MHIC #118450)
Two deck quotes that look far apart on price may not be describing the same job. The fix is a checklist: go through each quote item by item and write “included,” “extra” or “not mentioned” next to every line. Below is the checklist we’d use, with our own answers filled in as the yardstick.
On This Page
ToggleBefore anything else: the license
In Maryland, the Home Improvement Commission states that only MHIC-licensed contractors may contract with homeowners for home improvement work. You can look up any contractor on the Commission’s license search before you compare a single price. Ours is MHIC #118450.
The license matters for more than paperwork. According to the Commission, its Guaranty Fund compensates homeowners for actual monetary losses due to poor workmanship, and it applies only to work done by licensed contractors. Awards are capped at what you paid the contractor, up to $30,000.
The quote-comparison checklist
| Line to check | What to ask | Davis Construction |
|---|---|---|
| Permit | Who pulls it, and is it in the price? | We pull it; included |
| Inspections | Who meets the inspector? | We handle all three inspections and try to be on site when the inspector comes |
| Footings | How deep and how wide? | 24–30 in deep, 18 in wide; included |
| Framing lumber | What grade and treatment? | No. 1 grade, treated for ground contact, under wood and composite decks |
| Old deck removal | Demo, haul-away and dump fees included? | All three included |
| Railing | What type comes standard? | Wood on wood decks; white vinyl on composite |
| Border | Picture frame and breaker boards? | Single frame plus breakers included |
| Fasteners | Hidden or face-screwed? | Hidden on composite; Fiberon EDGE/EDGEX on Fiberon |
| Hardware near the water | Stainless or galvanized? | Stainless steel within 300 ft of salt water; hot-dip galvanized everywhere else |
| Steps | Priced how? | Per 4-ft step: composite $350/$450/$550, wood $330 or $530 lit |
| Workmanship warranty | How long, in writing? | One year |
| Payment schedule | How much up front, and when is the rest due? | 30% signing, 60% material on site and work starting, 10% after final inspection |
Your county’s adopted building code and its inspector have the final say.
How to use the checklist
Normalize the scope
If one quote leaves out demolition or dump fees, you’ll be paying for those somewhere. Add a realistic amount to that quote before you compare. The same goes for railings: a quote with no railing is not comparable to one that includes it.
Match the decking line, not just “composite”
“Composite” covers a wide range. On a 12×25, our standard composite totals go from $24,000 (Fiberon Good Life Weekender or Deckorators Venture) to $30,000 (TimberTech Terrain+). Make sure two quotes name the same brand and line. Our brand pages for Trex, TimberTech, Fiberon and Deckorators list the lines we install.
Count the stairs and railing sections
Ask each contractor how many steps and how many railing sections they priced, and at what rate. Our upgrades are listed on the deck pricing page, from aluminum pickets at +$50 per 6–8 ft section to cable at +$200–$300.
Ask what happens if the old frame is rotten
This question matters most on a re-deck. Our price absorbs up to two damaged 12-foot joists. If there’s more, you see it with your own eyes and approve a written change before anything else gets built. Get every contractor’s answer to this in writing.
What Maryland says a contract must contain
The Commission’s contract page lists what a home improvement contract has to include. Among them:
- The contractor’s name, address and MHIC license number
- A description of the work and the materials to be used
- Approximate start and substantial completion dates
- Notice that anyone can ask the MHIC about a contractor, and a notice about the Guaranty Fund
- Signatures from both parties, in writing
The same page caps the deposit at one-third of the contract price and says no payment can be taken before the contract is signed. A proposal that asks for half down up front doesn’t meet that rule.
Comparing the extras that matter to you
Once the base scope lines up, compare the features you actually want. A few of our prices for reference: a 4×4 composite landing is $1,500, $1,800 or $2,400; gates are $500–$550 each; a double picture frame with double breaker is about $1,500 more than the single frame; RainEscape under-deck drainage on a 12×12 is $2,304–$2,880.
Quote-comparison questions
Should I pick the lowest number?
Pick the lowest number for the same scope. Before you do, check the cheapest-looking quote against the checklist for the permit, the haul-away and the railing.
Is a 3D drawing worth asking for?
It helps you compare layouts, not just prices. We include one free with every quote; see our 3D deck design page.
Does your price include the decking itself?
Yes. Materials, labor and hardware are all in the total, so you aren’t buying boards separately. Active-duty military and veterans also get 10% off, up to $1,000.
Before you sign with anyone, run through these questions for a deck builder.
Put us on your list
Bring your other quotes to the estimate and hold them up against ours line by line. Book a free estimate here or call 240-794-2274.
Sources: Maryland Home Improvement Commission (license lookup, Guaranty Fund); MHIC, Home Improvement Contracts (contract contents, deposit limit). Davis Construction inclusions and prices come from our own price list.