By Tony Davis, owner, Davis Construction & Home Improvement (MHIC #118450)
If your home is within 1,000 feet of tidal water or tidal wetlands, it’s in Maryland’s Chesapeake Bay Critical Area, and a deck there gets an extra layer of review. The big questions are whether your deck lands in the shoreline Buffer and how it counts toward lot coverage. Here’s what the state and our counties say, in their words.
On This Page
ToggleWhat the Critical Area is
Maryland’s Critical Area Commission defines it this way: “The Critical Area includes all land within 1,000 feet of Maryland’s tidal waters and tidal wetlands.” It also covers the Bay and the Atlantic Coastal Bays, their tidal tributaries, and the land under those waters.
The Commission’s FAQ says most residential building permits don’t need Commission review and “can be handled by the local government.” In St. Mary’s and Calvert, the county’s own permit pages build the Critical Area review into the building permit process.
The Buffer: the first 100 feet
Inside the Critical Area is the Buffer. Per the Commission, “The minimum Buffer width is 100-feet; however, on some properties it may be wider,” for example where there are steep slopes, wetlands or sensitive soils. The Commission’s guide “Becoming Bay Smart” describes the Buffer as starting at mean high water of tidal waters, the edge of a bank of a tributary stream, or the edge of a tidal wetland. In new subdivisions in the Resource Conservation Area, it lists a 200-foot Buffer.
The same guide’s summary for the Buffer is short: “In general, no new development permitted.” The FAQ says structures generally have to be located outside the Buffer unless “an applicant works with the local approving authority to obtain a variance.”
For a deck, that’s the first thing to figure out. A deck footprint that stays outside the Buffer is a very different permit conversation than one that reaches into it.
Lot coverage and decks
The second question is lot coverage. “Becoming Bay Smart” says lot coverage includes “the ground area covered or occupied by a stairway or impermeable deck.” It also lists an exclusion: “A deck with gaps to allow water to pass freely.”
In the Limited Development Area and Resource Conservation Area, the guide says lot coverage is generally limited to 15%, with the LDA limit depending on lot size and grandfathered status. Your county applies the exact figure for your lot, so check with them before you settle on a size.
How a specific deck design gets counted is the county’s call. Ask early, while the design is still on paper.
How each county handles it
St. Mary’s County
St. Mary’s spells out its Critical Area permit requirements in Customer Assistance Guide #9. The plan you submit has to map the waterline at mean high water, any wetlands or streams, trees and shrubs, how far the digging and grading will reach, and everything built on the lot, existing or new. A deck counts as one of those built surfaces in the guide’s terms, so its size and position appear on the plan. Where required, the county may also call for a Critical Area Planting Agreement.
Calvert County
In Calvert, a home deck inside the Critical Area means filling out the county’s Critical Area Worksheet along with the permit application. The county posts an interactive Critical Area map so you can see whether your parcel is inside.
Charles County
The state’s 1,000-foot rule applies to Charles County land near tidal water just as it does elsewhere. We didn’t find a Charles County page specific to Critical Area decks while writing this, so ask Charles County Planning and Growth Management about current submittal requirements for your property.
Planting and mitigation
The Commission’s FAQ notes that when you build a house or an addition outside the Buffer, “Planting is required unless the Buffer is already fully forested,” and that vegetation removed in the Buffer “must be replaced,” with removal of a dead tree as the one exception. “Becoming Bay Smart” lists replacement ratios for clearing existing forest in the RCA and LDA: 1 to 1 for up to 20%, 1.5 to 1 between 20% and 30%, and 3 to 1 plus a variance over 30%. If no trees have to come out for the deck, those forest-clearing ratios don’t come into play.
One line in the Commission’s guide sums up the whole topic: “ALL DISTURBANCE IN THE CRITICAL AREA REQUIRES A PERMIT.”
How we approach a Critical Area deck
- Permit: in St. Mary’s and Calvert, the Critical Area review rides along with the building permit. We pull the permit for every job, and we handle each inspection.
- Design first: a free 3D drawing comes with every quote, so you can see the deck’s size and position before a plan goes to the county.
- Hardware: within 300 feet of salt water we use stainless steel hardware; everywhere else we use hot-dip galvanized. Your county’s adopted building code and its inspector have the final say.
- Price: Critical Area or not, we don’t bill the permit separately; it’s part of the deck total, as are footings and removing and disposing of an old deck. A 12×16 covered deck, for example, runs $26,880–$29,760 in wood and $28,800–$31,000 in composite. Open-deck totals by size are in our deck price list, and covered builds are on our covered decks page.
For next steps on design and materials, our under-deck drainage page and composite decks page are good next reads.
Critical Area questions
My house was built before these rules. Am I exempt?
The state’s guide says the LDA lot coverage limit depends partly on grandfathered status, so older lots can be treated differently. Your county decides how that applies to your parcel.
Can I replace an old deck in the Buffer?
That’s a county decision under its Critical Area program. The Commission says new structures generally belong outside the Buffer unless a variance is granted, so ask before you plan a bigger replacement.
Who files the Critical Area paperwork?
In St. Mary’s and Calvert, it’s part of the building permit application, and we pull the permit.
County-specific steps are in our Calvert deck permit walkthrough and the St. Mary’s permit guide.
Waterfront lot? Start with a visit
A waterfront deck starts with your lot and the county map. Book a free estimate or call 240-794-2274. Military families take note: veterans and active-duty personnel receive 10% off, with the discount topping out at $1,000.
Sources: Maryland Critical Area Commission (DNR), FAQs; Maryland Critical Area Commission, “Becoming Bay Smart”; St. Mary’s County CAG #9, Building Permits in the Critical Area; Calvert County, Deck – Residential. Prices and process come from Davis Construction’s own price list.